High-density AI infrastructure

2.5 MW of AI capacity, built in a factory.

Twenty-four rack positions, warm-water direct liquid cooling, integrated power and heat rejection. Electrical, thermal, control, fire, and monitoring systems are tested together before the modules ship.

2.5 MW
Modeled IT peak per unit
24
Rack positions
1,152
GPUs, reference configuration
192 kW
Busway provisioning per rack
41/51 °C
Facility water supply and return

Integrated system architecture

Three factory-built modules, and the plant that rejects their heat.

The platform separates power, IT, and facility functions into modules that are built and tested in a factory. Those three, with the external heat rejection plant, make one 2.5 MW unit under one coordinated power and thermal architecture. The arrangement repeats from site to site, so each project integrates against the same utility, generator, network, and water interfaces.

Energy module

Medium and low voltage interface, transformers, UPS, A/B distribution, batteries, and generator interfaces.

IT module

24 rack positions, high-density busway, rack liquid interfaces, residual air cooling, and technical access.

Facility module

Pumps, filtration, controls, air-side cooling, fire protection, and building management and monitoring interfaces.

External heat rejection

The plant sits outside the modules at 2.50 MW duty. Dry operation is the normal mode, with tank-fed adiabatic assist when the climate calls for it.

Built for high-density AI

Standard on every unit.

  1. 01 2.5 MW modeled IT peak per unit
  2. 02 All 24 rack positions populated in the reference layout
  3. 03 16 GB300 NVL72 racks plus 8 network and support racks
  4. 04 Warm-water direct liquid cooling at 41/51 °C
  5. 05 Dry-first heat rejection with no permanent utility water connection
  6. 06 Independent A/B rack power paths, with 2N UPS available as an option
  7. 07 Integrated fire protection, access control, and monitoring
  8. 08 Factory acceptance testing before shipment, site acceptance testing on commissioning

Thermal management

The site needs no water connection.

Warm water at 41/51 °C carries the GPU heat. A small air-side system takes the rest. Heat rejection runs dry until roughly 39 °C ambient, then draws on a tank, so nothing has to be plumbed to a utility.

Dry operating mode
0 water
Adiabatic transition
≈39 °C
High-ambient reference
50 °C
Concept render of a modular compute deployment in high desert terrain.

Reference technical configuration

Specifications.

Values below are the current engineering reference for the GB300 configuration. Rack interfaces, secondary loop conditions, and the certification path follow the rack OEM selected for the project.

Compute

GB300 NVL72 rack positions 16
Network and support rack positions 8
GPUs, reference configuration 1,152
Grace CPUs, reference configuration 576
Modeled rack power, GB300 EDPp ≈155 kW

Power

Modeled electrical peak, IT 2.536 MW
Reference gross facility interface ≈3.0 MW
Busway provisioning per GB300 rack 192 kW
Distribution basis Independent A/B paths; optional 2N UPS
UPS autonomy, budgetary basis 15 minutes

Cooling

Direct liquid cooling design capacity 2.100 MW
Air-side design capacity 0.280 MW
Total thermal design basis 2.380 MW
Heat rejection duty capacity 2.500 MW
Facility water supply and return 41/51 °C

Water and footprint

Normal operating mode Dry, no water
Adiabatic transition reference ≈39 °C ambient
Utility water connection Not required
On-site storage equivalent 100 m³
IT module envelope 16.2 m × 6.8 m

Flow rates, rack-level thermal load, busway installed capability and module zoning are in the technical brief.

Deployment

From site review to commissioning.

  1. 01

    Site and utility review

    Load, utility service, water availability, and site climate against the unit footprint.

  2. 02

    Interface freeze

    Rack geometry, lifting routes, liquid feed, cable entry, and clearances are fixed after OEM selection and transport review.

  3. 03

    Factory build and test

    Mechanical and electrical systems are integrated and functionally tested before shipment.

  4. 04

    Delivery and connection

    Modules are set, then connected to utility, generator, network, and water interfaces.

  5. 05

    Site test and commissioning

    Site acceptance testing, then handover against the project commissioning scope.

The site provides

  • Prepared ground for the unit footprint and service clearance
  • Utility electrical service to the energy module interface
  • Network connectivity
  • Local permitting, grounding, and metering coordination
  • Water for adiabatic assist where the climate requires it, from on-site storage

The unit includes

  • Energy module with transformers, UPS, batteries, and generator interfaces
  • IT module with 24 rack positions, busway, and rack liquid interfaces
  • Facility module with pumps, filtration, controls, and air-side cooling
  • External heat rejection plant arranged to the site climate
  • Fire protection, access control, leak detection, and monitoring

Scale

The same unit, repeated.

One unit

2.5 MW, 24 rack positions.

Three modules and one heat rejection plant on a single prepared pad.

Phased site

Add units as power is confirmed.

Each unit repeats the same power and thermal architecture, so later phases integrate the same way as the first.

Campus

One set of interfaces across phases.

Utility, generator, network, and water interfaces stay consistent as the site grows.

Overhead concept render of repeated units on one prepared pad.

Engineering basis

The architecture is fixed. The rack interfaces follow your OEM.

The unit is engineered around high-density GB300 NVL72 deployment requirements. Final power interfaces, rack CDU implementation, network fabric, and certification requirements are coordinated with the selected OEM during detailed engineering.

The platform supports concurrently maintainable, Tier III-equivalent project objectives, subject to the final project redundancy matrix, utility demarcation, and certification scope. Installed feeder capability is a design and protection value and is not a figure for simultaneous IT consumption.

Check equipment lead times →

Tell us the load and the date.

Send the capacity you need, whether that figure is IT load or facility load, and the quarter it has to be live. We come back with scope and schedule.

Modular data center

Request the technical brief

The reference configuration in full: rack layout, power and cooling design basis, heat rejection, water strategy, and module dimensions. Tell us who you are and we will send it over.

Teraplex uses this information to fulfill your request. Marketing consent is optional. Privacy policy.